[libre-riscv-dev] getting important: need to create the project plan, involves estimating times for tasks (and creating them)

Aleksandar Kostovic alexandar.kostovic at gmail.com
Wed Apr 24 20:06:09 BST 2019


so i can lay out the plan for the FPU:
- create sqrt function
- create test for sqrt function
- run the tests for the whole FPU

I dont have a time frame on that but i do think it will be done by the end
of May(design can be done fairly quickly, but we need to run LOTS of tests
to prove its working).

On Wed, Apr 24, 2019 at 12:51 PM Luke Kenneth Casson Leighton <lkcl at lkcl.net>
wrote:

> ok so nice conversation with michiel, he said basically don't worry
> about fine-level granularity, just make some rough cost estimates, and
> if they think it's like an order of magnitude out, they'll query it,
> otherwise it can be adjusted as progress is made.
>
> the main thing they want is a list of:
>
> * summary of milestone
> * one/two-line paragraph
> * budget (paid on completion)
>
> also, because we have already started, anything done since february
> 1st they can consider *retrospectively* to include as "done" and pay
> for.
>
> so, jacob, for example, creating a "group" of those Kazan tasks, and
> allocating them to a given milestone, that would work.
>
> we want to put budgets on the *leaf* node sub-tasks obviously, not
> further up, otherwise there would be double-counting.
>
> i will add a field "budget" to the bugtracker database.
>
> l.
>
> _______________________________________________
> libre-riscv-dev mailing list
> libre-riscv-dev at lists.libre-riscv.org
> http://lists.libre-riscv.org/mailman/listinfo/libre-riscv-dev
>


More information about the libre-riscv-dev mailing list